Sample Migration Plans
These examples illustrate typical outputs generated by the Agentic ERP Migration Planner for common migration scenarios. All plans are hypothetical but based on real-world patterns and benchmarks.
Example 1: SAP ECC → S/4HANA (Global Manufacturing Company)
Input Summary
- Current system: SAP ECC 6.0 with 8,000+ custom Z-objects
- Modules: FI, CO, MM, SD, PP, QM, WM
- Data volume: 2.5 TB, 15 years history
- Integrations: 45 third-party systems
- Users: 5,000 across 12 countries
Recommended Approach: Phased Brownfield
Convert existing ECC system to S/4HANA while selectively innovating with new functionality.
Phased Plan
| Phase |
Scope |
Duration |
Go-Live |
| Phase 1 |
Finance & Controlling (global template) |
9 months |
Q3 2026 |
| Phase 2 |
Procurement & Manufacturing (Europe & NA) |
12 months |
Q3 2027 |
| Phase 3 |
Sales & Distribution + remaining regions |
10 months |
Q2 2028 |
Key Risks Identified
- High: Custom code volume — recommend selective clean-core approach
- Medium: Multi-country rollout — language and legal requirements
- Medium: Data archiving strategy for historical data
Estimated Cost
$28–35 million over 30 months (including licensing, consulting, internal resources)
Example 2: Oracle EBS → Oracle Cloud ERP (Mid-Size Retail Chain)
Input Summary
- Current system: Oracle EBS 12.1
- Modules: Financials, Supply Chain, HR
- Data volume: 800 GB
- Customizations: Moderate (1,200 custom objects)
- Users: 800 across 3 countries
Recommended Approach: Hybrid Lift-and-Shift with Selective Reimplementation
Phased Plan
| Phase |
Scope |
Duration |
| Phase 1 |
Financials (lift-and-shift) |
8 months |
| Phase 2 |
Supply Chain reimplementation |
10 months |
| Phase 3 |
HR and remaining functions |
6 months |
Key Risks Identified
- High: Integration with POS systems
- Medium: Change management for supply chain processes
Estimated Cost
$12–16 million over 24 months
Example 3: Legacy Custom ERP → Dynamics 365 (Financial Services Firm)
Input Summary
- Current system: 20-year-old custom COBOL mainframe
- Heavy regulatory reporting requirements
- Data volume: 1.2 TB
- Users: 1,200
Recommended Approach: Parallel Run with Gradual Cutover
Key Considerations
- Run new D365 system in parallel for 6 months
- Regulatory reporting validated on both systems
- Gradual user migration by department
Estimated Timeline
36 months total (including 6-month parallel run)